DEDEDO COMBUSTION TURBINE SUBSTATION

OWNER—GUAM POWER AUTHORITY
Agana, Guam

TriAxis provided complete design and services during construction for the addition of a second 22 MW combustion turbine generator to an existing facility. The project included the addition of a ring bus substation for interconnection to the utilities transmission system. The ring bus consisted of two 18/24/30 MVA generator step-up transformer positions and two 34.5-kV line positions.