Mobile Substation Specifications
|
Consumers Power Inc.
|
Philomath , Oregon
|
115 x 69, 12.47 x 24.9
|
10
|
Mobile Substation
|
Develop specification for dual voltage high side and low side mobile substation.
|
2011
|
|
Desert Claim
|
enXco/DEA
|
San Diego, California
|
230
|
200
|
Transmission, Distribution
|
Develop preliminary One Line, General Plan & transformer spec
|
2011
|
|
Jerome Prairie
|
PacifiCorp/DEA
|
Portland, Oregon
|
115
|
20
|
Distribution
|
Replace transformer fuses with circuit switcher & relays
|
2011
|
|
Farmington Substation
|
PacifCorp/DEA
|
Salt Lake City, Utah
|
138
|
30
|
Distribution
|
Add 2nd transformer and cap bank, add two new feeders
|
2011
|
|
Lemolo 1
|
PacifCorp/DEA
|
Portland, Oregon
|
115
|
N/A
|
Distribution
|
Replace existing disconnect switch.
|
2011
|
|
Standard Foundation Design
|
Eugene Water and Electric Board
|
Eugene, Oregon
|
115
|
N/A
|
Distribution
|
Develop a standard breaker and transformer foundation.
|
2011
|
|
Mt. Si Substation
|
Puget Sound Energy/DEA
|
Seattle, Washington
|
138
|
25
|
Distribution
|
Revised station service design to use 15kV padmount switch
|
2011
|
|
Seneca 69-kV Str. Analysis
|
Eugene Water and Electric Board
|
Eugene, Oregon
|
115
|
N/A
|
Distribution
|
Perform structural analysis of existing standard structures
|
2011
|
|
Albina Substation
|
DEA/PacifiCorp
|
|
15
|
N/A
|
Distribution
|
Replaced existing 15-kV breakers
|
2011
|
|
Port of Morrow Substation 115-kV Breaker Addition
|
Umatilla Electric Cooperative
|
Hermiston, Oregon
|
115-12-47
|
2x 12/14, 30
|
Transmission, Distribution
|
Transmission breaker addition
|
2010
|
|
Hermiston Butte Substation 115-kV Ring Bus Expansion
|
Umatilla Electric Cooperative
|
Hermiston, Oregon
|
115-12.47
|
3x12/16/20
|
Transmission, Distribution
|
Ring bus and 3rd transformer bank addition
|
2010
|
|
Rocklyn Substation Rebuild
|
Inland Power and Light
|
Spokane, Washington
|
34.5-12.47
|
5/6.25
|
Distribution
|
Rebuild of existing distribution substation
|
2010
|
|
Day Mt. Spokane Substation (Slatt)
|
Inland Power and Light
|
Spokane, Washington
|
230-12.47
|
20/26/33
|
Distribution
|
Complete design
|
2010
|
|
Power Transformer Specifications (Rocklynn/Slatt)
|
Inland Power and Light
|
Spokane, Washington
|
230-12.47, 34.5-12.47
|
20/26/33, 5/6.25
|
Distribution
|
Transformer Purchase Specification Document
|
2010
|
|
Hinshaw Relay Setting Review
|
FPL Energy
|
Evanston, Wyoming
|
138-34.5
|
90/120/150
|
Wind Farm Step Up
|
Relay setting review and update
|
2010
|
|
Simpson Creek Relay Replacement
|
Consumers Power Inc.
|
Corvallis, Oregon
|
69/24.9
|
12-Oct
|
Distribution
|
Feeder relay replacement design
|
2010
|
|
Columbia Way Substation Rebuild
|
Cowlitz County PUD
|
Longview, Washington
|
115-13.09
|
2x30/40/50
|
Distribution
|
Added high side bus, moved transformers
|
2010
|
|
Cameron Substation Review #2 Check
|
PacifiCorp/DEA
|
Portland, Oregon
|
138/46
|
25 + 75
|
Transmission, Distribution
|
Owner
|
2010
|
|
Lester Substation
|
Consumers Power Inc.
|
Philomath, Oregon
|
69
|
12/16/2020
|
Distribution
|
Preliminary design for permit and property purchase
|
2010
|
|
115-kV Relaying Oly Pipe Substation
|
Cowlitz County PUD
|
Longview, Washington
|
115-13.2
|
10
|
Distribution
|
High side switch replacement and relay upgrade
|
2010
|
|